CONSTRUCTION, ERECTION AND PUTTING INTO OPERATION OF A RESEARCH PLATFORM IN THE NORTH SEA

BAU, AUFSTELLUNG UND INBETRIEBNAHME EINER FORSCHUNGS- UND ERPROPUNGSPLATTFORM IN DER NORDSEE

A platform was designed and erected in 30 m deep water. A reinforced concrete base was prefabricated, towed and placed on the ground by floating cranes. The support framework was made of steel pipes. The deck may accommodate 28 persons. A study was made about the wave effects on the supporting structure.