UNIQUE DRAINAGE SOLVES ICING IN RAILWAY TUNNEL

Solution to a severe icing problem in a tunnel section during relocation of 13 km of rail line necessitated by the Mica dam project in British Columbia is described. The method used to drain away seepage water in the tunnel resulted in the clearing of the blocked line, cut costs and saved valuable time in the relocation operation.

  • Corporate Authors:

    Southam Business Publications Limited

    1450 Don Mills Road
    Don Mills, ONo,   Canada 
  • Authors:
    • Kennedy, J
  • Publication Date: 1977-7

Media Info

Subject/Index Terms

Filing Info

  • Accession Number: 00167974
  • Record Type: Publication
  • Source Agency: Engineering Index
  • Files: TRIS
  • Created Date: Dec 27 1977 12:00AM