THE DB'S MUNICH TRACK RENEWAL SECTION WORKING ALTERNATELY ON TWO LINES IN 1975 USING A ROSTER SYSTEM AND TWO WORK CREWS (UP2)

BAUSTELLENSERIE 1975 DER DB MUECHEN IM ZWEISCHICHTEN SPRINGSYSTEM (UP2)

Munich's regional headquarters renewed 56.4 km of track on 13 sections of two different lines in less than 9 months in 1975. The schedule for this work was fixed so that the UP2 track renewal train was used alternatively on the two lines. The authors describes the results obtained and the experience acquired during this work.

  • Availability:
  • Corporate Authors:

    Dr Arthur Tetzlaff Verlag

    Niddastrasse 64
    Frankfurt am Main,   Germany 
  • Authors:
    • Kraft, W
    • Kaiser, D
  • Publication Date: 1976-3

Language

  • German

Media Info

  • Features: References; Tables;
  • Pagination: p. 103-106
  • Serial:
    • Eisenbahningenieur
    • Volume: 27
    • Issue Number: 3
    • Publisher: Tetzlaff Verlag GmbH
    • ISSN: 0013-2810

Subject/Index Terms

Filing Info

  • Accession Number: 00136419
  • Record Type: Publication
  • Source Agency: Engineering Index
  • Files: TRIS
  • Created Date: Aug 3 1976 12:00AM