QUICK BRIDGE REPAIR: A JOINT EFFORT

Article describing the combined efforts of Wisconsin Central railroad, and Osmose, a construction contractor, to restore two concrete bridges on an abandoned service line. With only three weeks' work time, the job was completed satisfactorily and under schedule. Provides detailed descriptions of the actual process and equipment involved in the restoration process.