MAJOR PROGRESS ON LT FLEET LINE INCLUDING TWO STEP-PLATE JUNCTION TUNNELS

The 21-mile twin-tunnel construction linking Baker Street station on the Bakerloo Stanmore branch with the new Fleet Line tunnels bored to Strand station which incorporate two step-plate junctions, these encircling existing running bore shells which are now to be dismantled. An enterprisingly executed task enabling train running to continue with a minimum of delay.

  • Availability:
  • Corporate Authors:

    Broadfields (Technical Publishers) Limited

    Little Leighs
    Chelmsford, Essex CMB 1PM,   England 
  • Publication Date: 1974-11

Media Info

Subject/Index Terms

Filing Info

  • Accession Number: 00083030
  • Record Type: Publication
  • Source Agency: Rail Engineering International
  • Files: TRIS
  • Created Date: Mar 26 1981 12:00AM