PLANNED BLASTING KEEPS ROAD AND TRAFFIC MOVING

DRILLING, BLASTING METHODS, AND EQUIPMENT THAT WERE USED DURING THE CONSTRUCTION OF 12.8 KM OF INTERSTATE 79 NEAR WESTON, WEST VIRGINIA, U.S.Z., ARE DESCRIBED. WITH LITTLE OR NO INTERRUPTION TO TRAFFIC ON A HIGHWAY WHICH RUNS THROUGH THE PROJECT AREA, 23000 CUBIC METRES OF ROCK PER DAY WERE MOVED. /TRRL/