SUB-BASE CONSTRUCTION OF JERSEY MARINE ROAD

THE ONLY MATERIAL AVAILABLE WAS WIND-BLOWN SAND, WHICH WAS STABILIZED WITH CEMENT AND CONSOLIDATED WITH 1-1/4 IN. SURCHARGE INTO 4-IN. THICK SUBBASE. COMPACTION WAS PERFORMED WITH HOLMAN SUBGRADE TYPE COMPACTOR FOLLOWED BY HOLMAN FINISHER. THE FINISHED SUBBASE WAS CURED FOR 3 TO 7 DAYS THEN SPRAYED WITH 55% BITUMEN EMULSION AT THE RATE OF 6 SQ. YDS. PER GALLON.