LIME RECLAIMS UNSTABLE INTERIOR SUBGRADE DURING CONSTRUCTION

Two acres of unstable subgrade required stabilization while construction was in progress. Four percent monohydrated lime at about 20 lb per sq yd served as the stabilizing agent. After a discharrow scarified the area, 25 tons of lime were spread. A dozer-disc combination worked over the area, and a pneumatic roller performed the sealing.