CURRENT WAVEFORM DISTORTION AT 25 KV SINGLE PHASE SUPPLY POINTS TO BRITISH RAILWAYS
The 132 kv current taken at the 132/25 kv substations supplying the British Railways 25 kv 50 Hz traction system is unbalanced, being single phase connected across two 132 kv system phases, and the waveform is distorted i.e. it contains harmonics. Both conditions can cause difficulties on the public supply network and require continuing investigation, since future expansion of the BR 25 kv electrified system is likely. However, this paper deals only with the harmonic aspects of the problem, the unbalance effects.
-
Supplemental Notes:
- Prepared for meeting April 22-24, 1974.
-
Corporate Authors:
Institution of Electrical Engineers
Savoy Place
London WC2R 0BL, NY England 10016-5997 -
Authors:
- Myles, A
- Howroyd, D C
- Publication Date: 1974
Media Info
- Features: References;
- Pagination: p. 241-245
-
Serial:
- Publication of: Institution of Electrical Engineers
- Issue Number: 110
- Publisher: Institution of Electrical Engineers
Subject/Index Terms
- TRT Terms: Electric power supply; Electrical systems; Interference; Railroad electrification
- Identifier Terms: British Rail
- Subject Areas: Energy; Railroads;
Filing Info
- Accession Number: 00128868
- Record Type: Publication
- Source Agency: Engineering Index
- Report/Paper Numbers: 112 Conf Publ
- Files: TRIS
- Created Date: Feb 4 1976 12:00AM