REPORT ON INTEGRATED STEAM POWER PLANT, PHASE 1, PART 7-B. SUMMARY REPORT

Plant design; Final selection of steam conditions; Heat balances; Electric load analysis; Arrangement of machinery and engineer's operating station; Manning; Rules deviations; Economics; Use of low cost residual fuel with the recommended plant; Recommendations for work to be done in phase 2.

  • Supplemental Notes:
    • See also PB-177855.
  • Corporate Authors:

    Newport News Shipbuilding and Drydock Company

    Engineering Technical Department
    Newport News, VA  United States 
  • Publication Date: 1962-11

Media Info

  • Pagination: 119 p.

Subject/Index Terms

Filing Info

  • Accession Number: 00027639
  • Record Type: Publication
  • Source Agency: National Technical Information Service
  • Contract Numbers: MA-2967
  • Files: TRIS
  • Created Date: Jul 9 1973 12:00AM