NS SAVANNAH PRIMARY COOLANT PUMP REPLACEMENT. PART 2: PUMP REPLACEMENT AND TEST

As a result of failure of two of the N.S. Savannah's four rotor primary coolant pumps, all four primary system pumps were replaced. This report covers the replacement of the pumps. The modifications and installation work was complete and the reactor critical within 94 days.