RAPID BRIDGE DECK REPLACEMENT: A FIELD DEMONSTRATION AND LOAD TEST. FINAL REPORT
This report describes a full-size field demonstration of a rapid bridge deck replacement concept put forward several years ago. The concept was to utilize a sand mortar made with a rapid setting epoxy to provide the shear tie between precast concrete deck panels and existing steel stringer beams. The demonstration site was a 50 ft simple span that serves as part of the SPUR 326 overpass over the AT&SF railroad tracks in downtown Lubbock, Texas. The demonstration bridge is one of two identical bridges, side-by-side; the other was redecked using a conventional poured-in-place technique. Eight precast panels, each 6 ft 3 in. x 45 ft x 8 in., were used to form the experimental deck. Each panel was cast with blockouts (holes) positioned directly over the supporting steel beams. When the original concrete deck was removed, the steel shear studs were cut away leaving the top of the flanges of the steel beams clean and flat. The precast panels were then positioned atop of the steel in an operation lasting less than 5 hours, the new steel studs were welded into place through the blockouts in about 4 hours, and then the panels were epoxied into place in less than 2 full working days. Subsequent load tests and deflection measurements were compared to results obtained using a 3D computer model. The comparison provided convincing evidence of the composite performance of the completed bridge.
- Record URL:
- Record URL:
-
Supplemental Notes:
- Research study title: Rapid Bridge Deck Replacement.
-
Corporate Authors:
Texas Transportation Institute
Texas A&M University System, 1600 E Lamar Boulevard
Arlington, TX United States 76011Texas State Department of Highways & Public Transportation
Transportation Planning Division, P.O. Box 5051
Austin, TX United States 78763Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC United States 20590 -
Authors:
- Osegueda, R A
- Noel, J S
- Publication Date: 1988-5
Media Info
- Media Type: Digital/other
- Features: Figures; References; Tables;
- Pagination: 73 p.
Subject/Index Terms
- TRT Terms: Bridge decks; Bridges; Composite structures; Deflection; Demonstration projects; Epoxides; Load tests; Performance; Precast concrete
- Uncontrolled Terms: Composite bridges; Rapid methods; Replacing
- Old TRIS Terms: Epoxy
- Subject Areas: Bridges and other structures; Design; Highways; Maintenance and Preservation; I24: Design of Bridges and Retaining Walls; I61: Equipment and Maintenance Methods;
Filing Info
- Accession Number: 00485596
- Record Type: Publication
- Report/Paper Numbers: FHWA/TX-88-324-5F, Res Rept 324-5F, TTI: 2-5-82-324-5F