SELECTION OF TUNNELLING FORMWORK
The article discusses a number of important points to consider before tunneling formwork is designed, including ground conditions, access, concreting limitations, availability of labour and local methods of construction. It advises that full trial assembly of the formwork must take place before equipment is delivered to site. This is not only for the manufacturers' purposes, but also for the contractors' inspection, as any changes or modifications required can be made more satisfactorily at this time rather than on site.
-
Availability:
- Find a library where document is available. Order URL: http://worldcat.org/issn/0041414X
-
Corporate Authors:
Morgan-Grampian Limited
30 Calderwood Street
London SE18 6QH, England -
Authors:
- Jeffery, R
- Publication Date: 1980-11
Media Info
- Pagination: p. 15-17
-
Serial:
- Tunnels & Tunnelling International
- Volume: 12
- Issue Number: 10
- Publisher: Progressive Media Markets, Ltd
- ISSN: 0041-414X
Subject/Index Terms
- TRT Terms: Concrete; Concrete construction; Contractors; Design; Linings; Tunnel lining; Tunneling
- Uncontrolled Terms: Design criteria
- Old TRIS Terms: Concrete tunnel liners; Forms; Tunnels and tunneling
- Subject Areas: Bridges and other structures; Construction; Design; Public Transportation;