TOUGH LOCATIONS IS CHOSEN FOR NEW-TYPE ROAD XING

Railbound concrete slabs were installed where heavy vehicular traffic from steel plant crosses over railroad diamond crossing. At the site selected for the crossing-slab installation the road from the steel plant uses the deck of a railroad lift bridge over the channel. Making a sharp turn to the left, this road crosses the railroad diamond crossing at an angle. Road traffic includes about 240 daily runs of heavy (60 tons) slag trucks, 20 coke-loaded trucks from the screening operation, 1000 automobiles steel-loaded flatbeds and a 64-ton pay-loader with chain-wrapped rubber-tires.

  • Availability:
  • Corporate Authors:

    Simmons-Boardman Publishing Corporation

    P.O. Box 350
    Bristol, CT  United States  06010
  • Publication Date: 1972-7

Media Info

  • Pagination: p. 20-22
  • Serial:

Subject/Index Terms

Filing Info

  • Accession Number: 00046694
  • Record Type: Publication
  • Source Agency: Engineering Index
  • Files: TRIS
  • Created Date: Sep 27 1973 12:00AM