DESIGN SECTION E006: GLENMONT SUBSURFACE INVESTIGATION- RETAINING WALLS TIE BREAKER AND SUBSTATIONS

RESULTS OF 27 BORINGS MADE AT VARIOUS LOCATIONS IN SECTION B006 OF GLENMONT ROUTE ALONG THE METROPOLITAN BRANCH OF THE B AND O RAILROAD RIGHT-OF-WAY ARE SUMMARIZED IN THIS REPORT. THE PURPOSE OF THE INVESTIGATION WAS TO EVALUATE SUBSOIL CONDITIONS AT A SERIES OF RETAINING WALLS, TIE-BREAKER STATIONS AND SUBSTATIONS. THE REPORT CONTAINS GEOLOGICAL SECTIONS AT THE LOCATION OF STRUCTURES, LOGS OF THE BORINGS, RESULTS OF LABORATORY TESTS ON SPLIT-SPOON AND UNDISTURBED SAMPLES AND CONCLUSIONS REGARDING SUBSOIL PROPERTIES. /AUTHOR/

  • Supplemental Notes:
    • Rept No MRWJ-72-72
  • Corporate Authors:

    Mueser, Rutledge, Wentworth & Johnston

    New York, NY  United States 
  • Publication Date: 1972-7-7

Media Info

  • Pagination: 48 p.

Subject/Index Terms

Filing Info

  • Accession Number: 00230294
  • Record Type: Publication
  • Source Agency: National Technical Information Service
  • Files: TRIS
  • Created Date: Dec 22 1973 12:00AM