CONSTRUCTION OF OHIO'S FIRST PRESTRESSED- CONCRETE BRIDGE

FORTY-FIVE PRECAST CONCRETE BEAMS, EACH HAVING AN OVERALL LENGTH OF 46 FT., WERE PRESTRESSED BY THE PRETNESIONED METHOD. THE BEAMS WERE CAST ON THE JOB SITE AND NOT IN A CENTRAL CASTING YARD. THE CONSTRUCTION PROCEDURE USED IS NOT SPECTACULAR BUT IS SIGNIFICANT FOR ITS SIMPLICITY. THIS PROJECT SHOWS THAT A CONTRACTOR CAN MAKE A SUCCESS OF HIS FIRST PRESTRESSED-CONCRETE JOB AND THAT PRETENSIONED PRESTRESSING CAN BE ACCOMPLISHED WITHOUT AN ELABORATE AND COSTLY SETUP.

  • Supplemental Notes:
    • Vol 23, No 5, PP 32-40, 12 FIG
  • Authors:
    • Vaught, G W
  • Publication Date: 1953-5