1 200 000 TONNES DE SABLE-LAITIER SUR LES AUTOROUTES DU SUD-OUEST
L'ARTICLE, ABONDAMMENT ILLUSTRE, DECRIT EN DETAIL LES TRAVAUX QUI VIENNENT D'ETRE REALISES POUR L'ACHEVEMENT DES DEUX LIAISONS A10 PARIS-BORDEAUX ET A63 BORDEAUX-BAYONNE. CES DEUX CHANTIERS AUTOROUTIERS TRES IMPORTANTS ONT FAIT APPARAITRE QUE LE TRAITEMENT AU LAITIER (QU'IL SOIT GRANULE OU PREBROYE) PERMET DE VALORISER DE FACON PARTICULIEREMENT INTERESSANTE LES SABLES FINS DE LA REGION SUD-OUEST, TOUT EN CONDUISANT A DES STRUCTURES PERFORMANTES, HOMOGENES, ET DE GRANDE FACILITE D'APPLICATION. LA POSSIBILITE DE TRAVAILLER EN FORTE EPAISSEUR ET A L'AVANCEMENT SUR UNE FORME PEU OU PAS CIRCULABLE, EN ECONOMISANT UN TRAITEMENT EVENTUEL POUR LA RENDRE TRAFICABLE, PARAIT ETRE L'INTERET MAJEUR DE CETTE TECHNIQUE, APPLIQUEE DE FACON INDUSTRIELLE ET A GRANDE CADENCE SUR LES CHANTIERS DE A10 ET DE A63.
-
Availability:
- Find a library where document is available. Order URL: http://worldcat.org/issn/0373708X
-
Authors:
- BASSET, M
- DUCHAILLUT, J -
- SABO, A
- Publication Date: 1982-1
Language
- French
Media Info
- Pagination: 9-27
-
Serial:
- LAIT HAUTS FOURN
- Issue Number: 50
- ISSN: 0373-708X
Subject/Index Terms
- TRT Terms: Base course (Pavements); Compaction; Construction sites; Freeways; Granulated slag; Pavement design; Sand; Slag
- Uncontrolled Terms: Laying
- ITRD Terms: A10; A63; 2752: Autoroute; 3628: Chantier; 3686: Compactage; 2961: Couche portante; 3055: Dimensionnement des chaussees; 4561: Laitier; 4560: Laitier granule; 4570: Laitier prebroye; 3623: Mise en oeuvre (appl); PHOSPHOGYPSE; 4105: Sable
- Subject Areas: Highways; Pavements; I33: Other Materials used in Pavement Layers; I52: Construction of Pavements and Surfacings;
Filing Info
- Accession Number: 01280416
- Record Type: Publication
- Source Agency: Institut Francais des Sciences et Technologies des Transports, de l'Aménagement et des Réseaux (IFSTTAR)
- Files: ITRD