ESTIMATING CONCRETE WORK - V

TECHNIQUES ARE DESCRIBED FOR REMOVING ITEMS FOR PRICING FROM THE QUANTITY TAKEOFF SHEETS TO THE RECAP SHEET. A LABOR OUTPUT TABLE IS PRESENTED FOR USE IN PRICING LABOR FOR FORM WORK ERECTION. THREE ITEMS ARE LISTED IN THE LABOR OUTPUT TABLE FOR FORM WORK: MATERIAL COST, ERECTION LABOR PER DAY AND STRIPPING LABOR PER DAY. THE ERECTION TIME INCLUDES A CARPENTER AND ONE-HALF LABORER PER DAY. THE STRIPPING TIME INCLUDES ONE LABORER PER DAY.

  • Availability:
  • Supplemental Notes:
    • Vol 12, No 10, PP 375-378, 1 FIG, 1 TAB
  • Authors:
    • Lejeune, E G
  • Publication Date: 1967-10